Aspose.Tasks for .NET V26.7Versión principal12 jul 2026
Funciones
You can now allow the passing of an instance of DbProviderFactory instead of ProviderInvariantName when using DbSettings.
Added support for reading Resource Codes from Primavera DB, XER, XML formats.
Correcciones
Fixed 'An item with the same key has already been added' exception when adding more than 1 view to the project.
Fixed "InvalidCast" exception when Microsoft.Data.Sqlite provider is used to read project from MS Project database.
Fixed import of activity codes and UDF from Primavera DB.
Fixed incorrect (multiplied by 100) values in baseline cost timephased data.
Fixed issue where Task.GetTimephasedData and Resource.GetTimephasedData dont't cut the resulting timephased data items according to the passed start/end argument.
Fixed "System.ArgumentException: An entry with the same key already exists" when reading a project from DB.
Aspose.Tasks for C++ V26.6Versión principal19 jun 2026
Funciones
Updated version of Aspose.Drawing dependency.
Added support for the reading of task expenses for Primavera DB format.
Changed source field of Task.Duration to "At completion Duration" instead of "Planned duration" when reading a project from Primavera formats.
Correcciones
Fixed calculation of BudgetedExpenseCost for Primavera XER and Primavera DB formats.
Fixed 'date cannot be DateTime.MinValue' exception when recalculating the project.
Fixed issue where Assignment.ActualStart date is not updated when parent task's start date is modified.
Fixed issue where task bar is rendered outside of Gantt chart's calendar's area.
Aspose.Tasks for Java V26.6Versión principal19 jun 2026
Funciones
Updated version of Aspose.Drawing dependency.
Added support for the reading of task expenses for Primavera DB format.
Changed source field of Task.Duration to "At completion Duration" instead of "Planned duration" when reading a project from Primavera formats.
Correcciones
Fixed calculation of BudgetedExpenseCost for Primavera XER and Primavera DB formats.
Fixed 'date cannot be DateTime.MinValue' exception when recalculating the project.
Fixed issue where Assignment.ActualStart date is not updated when parent task's start date is modified.
Fixed issue where task bar is rendered outside of Gantt chart's calendar's area.
Aspose.Tasks for Python via .NET V26.6Versión principal17 jun 2026
Funciones
Updated version of Aspose.Drawing dependency.
Added support for the reading of task expenses for Primavera DB format.
Changed source field of Task.Duration to "At completion Duration" instead of "Planned duration" when reading a project from Primavera formats.
Correcciones
Fixed calculation of BudgetedExpenseCost for Primavera XER and Primavera DB formats.
Fixed 'date cannot be DateTime.MinValue' exception when recalculating the project.
Fixed issue where Assignment.ActualStart date is not updated when parent task's start date is modified.
Fixed issue where task bar is rendered outside of Gantt chart's calendar's area.
Aspose.Tasks for .NET V26.6Versión principal16 jun 2026
Funciones
Updated version of Aspose.Drawing dependency.
Added support for the reading of task expenses for Primavera DB format.
Changed source field of Task.Duration to "At completion Duration" instead of "Planned duration" when reading a project from Primavera formats.
Correcciones
Fixed calculation of BudgetedExpenseCost for Primavera XER and Primavera DB formats.
Fixed 'date cannot be DateTime.MinValue' exception when recalculating the project.
Fixed issue where Assignment.ActualStart date is not updated when parent task's start date is modified.
Fixed issue where task bar is rendered outside of Gantt chart's calendar's area.
Aspose.Tasks for Java V26.5Versión principal26 may 2026
Funciones
Made Rsc.Start and Rsc.Finish calculated-on-demand properties.
Correcciones
Fixed sort order of leaf tasks when reading a project from XER, Primavera XML or Primavera DB.
Fixed issue where overtime timephased data is shown incorrectly in MS Project.
Fixed calculation of assignment's fields when ActualOvertimeWork is set.
Aspose.Tasks for C++ V26.5Versión principal23 may 2026
Funciones
Made Rsc.Start and Rsc.Finish calculated-on-demand properties.
Correcciones
Fixed sort order of leaf tasks when reading a project from XER, Primavera XML or Primavera DB.
Fixed issue where overtime timephased data is shown incorrectly in MS Project.
Fixed calculation of assignment's fields when ActualOvertimeWork is set.
Aspose.Tasks for Python via .NET V26.5Versión principal22 may 2026
Funciones
Made Rsc.Start and Rsc.Finish calculated-on-demand properties.
Correcciones
Fixed sort order of leaf tasks when reading a project from XER, Primavera XML or Primavera DB.
Fixed issue where overtime timephased data is shown incorrectly in MS Project.
Fixed calculation of assignment's fields when ActualOvertimeWork is set.
Aspose.Tasks for .NET V26.5Versión principal21 may 2026
Funciones
Made Rsc.Start and Rsc.Finish calculated-on-demand properties.
Correcciones
Fixed sort order of leaf tasks when reading a project from XER, Primavera XML or Primavera DB.
Fixed issue where overtime timephased data is shown incorrectly in MS Project.
Fixed calculation of assignment's fields when ActualOvertimeWork is set.