Aspose.Tasks for Java V26.4

Released: Apr 23, 2026

V26.4 中的更新

修补程序

  • Fixed incorrect recalculation of Actual Work timephased data when changing resource base calendar and adding exceptions.
  • Fixed incorrect calculation of summary tasks after modification of Task.Finish.
  • Fixed incorrect cascading recalculation of '% complete' and '% work complete' fields.
  • Fixed issue where actual work distribution is changed when calendar exception is added to the calendar.
  • Fixed issue with reading of values of enterprise extended attribute with type = Cost for the specific file.
  • Fixed issue with writing of Outline Code values to MPP.
  • Fixed issue where assignments not aligned with parent task become aligned after changing task duration.
  • Fixed issue where actual assignment work TD is corrupted when task calendar is modified.
  • Fixed issue where MS Project removes split when recalculating project containing non-working split between Stop and Resume dates.
  • Adding calendar exceptions changes Actual Work distribution after save.
  • Changing resource base calendar and adding exceptions shifts Resume time and alters Actual Work.