Aspose.Tasks for Java V25.2

Released: Feb 21, 2025

Mises à jour de V25.2

Correctifs

  • Baseline work discrepancies in task usage view - incorrect rollups and Missing Timephased Data.
  • Fixed incorrect dates of timephased data start/finish in some cases.
  • Fixed issue where zero baseline cost timephased data is not shown when opening MPP file using MS Project.
  • Fixed issue where task start is not adjusted to Prj.DefaultStartTime when task start is set to a date without time.
  • Fixed issue where timephased data is generated incorrectly when assignment is started before working hours (MPP).
  • Fixed issue where cost timephased data is shown incorrectly when MPP file is opened by MS Project.
  • Fixed calculation of baseline cost timephased data.